While traffic may be slow going, work to install a new water line is progressing on Windley Key in Islamorada.
Having completed several miles of water line installation on Upper Matecumbe Key, crews have installed more than 1,500 feet of new transmission main on Windley Key. FKAA says crews are nearly one-third completed on the new pipe installation phase.
With the Fourth of July bringing heavy traffic, a rolling lane closure for the project will be suspended through midnight on Monday, July 8, when work will resume. More information is at fkaa.com or on Facebook or X.